Ryan Corner Wind Farm GPG Naturgy Group Background The Ryan Corner Wind Farm site is located in South-Western Victoria, 16.5km north-west of Port Fairy within the Moyne Shire. The wind farm comprises 52 turbines with a total output of approximately 218.4MW. It will connect to the grid via a 132kV overhead transmission circuit to the existing 500kV Tarrone Terminal Station. All permits and management plans have been endorsed for the wind farm, the Tarrone North terminal station and the connecting transmission line and are available on the web site at https://ryancornerwindfarm.globalpower-generation.com.au/the-project/relevant-documentation/. Construction Update The weather has been consistent, and construction is progressing well. 18 turbine foundations have been poured and work has commenced on 16 more. After the pouring, testing of the foundations takes place before backfilling. The concrete for the foundations is supplied by the on-site batch plant. About 100 concrete truck loads are delivered to the concrete pumps to pour each foundation. The Youls Road upgrade is nearing completion, a final spray seal is still required before it is ready to take the delivery of the turbine components. Work is progressing on the onsite collector substation, transmission line and the Tarrone terminal station. The access tracks along the transmission line are completed and poles will start to be erected in the coming weeks. Weekly construction updates along with the monthly newsletter can be found on the web site https://ryancornerwindfarm.globalpower-generation.com.au. Community Engagement and Benefit Sharing The Ryan Corner Community Engagement Committee meets six weekly and is composed of community members, a Moyne Shire councillor and representatives from GPG. Copies of minutes are available on the Moyne Shire website. The Community Engagement and Benefit Sharing Plan associated to the project includes a Neighbour Benefit Program to ensure the financial benefits of the proposed project will be shared with those closest to the wind farm. Additionally, a Community Benefit Program will provide funding to develop or implement local community projects or initiatives in the area. Free Call: 1800 457 181 Email: ryancornerwindfarm@globalpower-generation.com.au Website: https://ryancornerwindfarm.globalpower-generation.com.au Mail: Ryan Corner Development Pty Ltd, Suite A, Level 3, 73 Northbourne Avenue, Canberra ACT 2601 VR4790602 Ryan Corner Wind Farm GPG Naturgy Group Background The Ryan Corner Wind Farm site is located in South - Western Victoria , 16.5km north - west of Port Fairy within the Moyne Shire . The wind farm comprises 52 turbines with a total output of approximately 218.4MW . It will connect to the grid via a 132kV overhead transmission circuit to the existing 500kV Tarrone Terminal Station . All permits and management plans have been endorsed for the wind farm , the Tarrone North terminal station and the connecting transmission line and are available on the web site at https://ryancornerwindfarm.globalpower-generation.com.au/the-project/relevant-documentation/ . Construction Update The weather has been consistent , and construction is progressing well . 18 turbine foundations have been poured and work has commenced on 16 more . After the pouring , testing of the foundations takes place before backfilling . The concrete for the foundations is supplied by the on - site batch plant . About 100 concrete truck loads are delivered to the concrete pumps to pour each foundation . The Youls Road upgrade is nearing completion , a final spray seal is still required before it is ready to take the delivery of the turbine components . Work is progressing on the onsite collector substation , transmission line and the Tarrone terminal station . The access tracks along the transmission line are completed and poles will start to be erected in the coming weeks . Weekly construction updates along with the monthly newsletter can be found on the web site https://ryancornerwindfarm.globalpower-generation.com.au . Community Engagement and Benefit Sharing The Ryan Corner Community Engagement Committee meets six weekly and is composed of community members , a Moyne Shire councillor and representatives from GPG . Copies of minutes are available on the Moyne Shire website . The Community Engagement and Benefit Sharing Plan associated to the project includes a Neighbour Benefit Program to ensure the financial benefits of the proposed project will be shared with those closest to the wind farm . Additionally , a Community Benefit Program will provide funding to develop or implement local community projects or initiatives in the area . Free Call : 1800 457 181 Email : ryancornerwindfarm@globalpower-generation.com.au Website : https://ryancornerwindfarm.globalpower-generation.com.au Mail : Ryan Corner Development Pty Ltd , Suite A , Level 3 , 73 Northbourne Avenue , Canberra ACT 2601 VR4790602